NTDC completes 133 km 2nd Phase of 500 kV Neelum Jhelum Transmission Line
LAHORE:National Transmission and Despatch Company Limited (NTDC) has successfully completed and energized the 133 km long 2nd phase of 500 kV Neelum Jhehlum Double Circuit Transmission line and energized it successfully. Now the power generated through 969 MW Neelum Jhehlum Hydropower Project will be dispatched directly to 500 kV Nokhar (New Ghakkar) Grid Station which […]